Backlog
All approved work that has not been completed yet. Maintenance teams track backlog in weeks of crew capacity to know if they are keeping up.
Where in Maximo
Work Order Tracking query; Start Center result sets
At Riverbend TP1 has 620 hours of approved MECH backlog and 3 mechanics, so about 5 weeks of backlog.
Related Terms
Verify in IBM Docs: IBM Docs > Maximo Manage > Work management